On September 12th, 2019, a major utility company in the Chicago area suffered a critical failure when one of their transformers caught fire and was destroyed. The utility company needed to get the transformer replaced quickly in order to maintain grid commitments and...
by Caroline Ko | Jan 13, 2020 | Case Studies
OVERVIEW / / Logisticus was contracted by a customer to move one 420,000 lb 840MVA Royal Smit transformer from one substation to another. Frost Law (Seasonal Weight Restrictions), the area of transport, and some infrastructure issues posed unique challenges. Read on...
by Caroline Ko | Aug 28, 2013 | Case Studies
WESTERN NEW YORK – JULY-AUGUST 2013 Logisticus Group® operated on a wind turbine project in Western New York assisting our customer with Risk Mitigation and Delivery Coordination of major wind turbine components. Field Operatives (FO’s) were first stationed at a...
by Caroline Ko | Jul 28, 2013 | Case Studies
Logisticus Group® was contracted to deliver 2 Wind Blade Molds – door to door from Northeastern United States to Eastern Europe. Our team conducted a multitude of cost/benefit analyses, determining the most cost effective logistics strategy to optimize transit...
by Caroline Ko | Jun 28, 2013 | Case Studies
Logisticus Group® was engaged to investigate transportation of a newly re-designed Wind Tower to be launched in the North American market. We performed detailed Route Feasibility Assessments in two regions of the US and Canada, working with multiple State DOT’s,...
by Caroline Ko | May 16, 2013 | Case Studies
NORTHWESTERN MA For a wind turbine project located in northwestern Massachusetts, all routes leading to the project site were on narrow, secondary roads that consisted of old, diminishing infrastructure. The team carried out very detailed and careful pre-planning...